(a) As long as you don't enter into a contract/appointment, you can't be liable.
(b) A professional designer in the construction sector can owe a duty of care in tort, which imposes liability for pure economic loss.
(c) If it exists, a professional's liability for pure economic loss covers only advice given, not other services that are performed, such as inspecting the execution of works by a contractor.
(d) You should always refuse a friend's request for advice.
(a) Oh no it doesn't.
(b) Oh yes it does.
(a) The fact that the other party's representatives favoured using this arbitrator and tried to exclude other arbitrators from being nominated without legitimate reasons. (This fact had been revealed by Ramsey J's earlier judgment in Eurocom Ltd v Siemens plc [2014] EWHC 3710 (TCC), in relation to potential adjudicators.)
(b) The arbitrator's response to requests for information was evasive, defensive and unjustified.
(c) The arbitrator's defensive and hostile stance when he convened a hearing.
(d) The fact that the arbitrator had acted so frequently as an arbitrator or adjudicator in cases where the other party's representatives were involved.
(e) The arbitrator's aggressive and unapologetic witness statement opposing the section 24 application.
(a) There is no point setting out interim payment dates beyond December. After all, the grotto will be complete by then.
(b) If the work does continue into next year, you will still be able to claim monthly interim payments. That is an implied term of the contract.
(c) If the work does continue into next year, this payment mechanism does not comply with the requirements of section 109 of the Housing Grants, Construction and Regeneration Act 1996 (Construction Act 1996). Therefore the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649) (Scheme for Construction Contracts 1998) will apply and confer a statutory right on you to claim monthly interim payments from January 2017 until practical completion.
(d) You will not be able to claim any interim payments if the work continues after the end of December and must wait until the final payment date for any further payment.
(a) The Construction (Design and Management) Regulations (SI 2015/51).
(b) The Construction Products Regulations 2013 (SI 2013/1387).
(c) The Party Wall etc. Act 1996.
(d) Late Payment of Commercial Debts (Interest) Act 1998.
(a) An extension of time will always be added contiguously to the previous date for completion, not discontinuously in discrete periods of time. This applies even if the contractor is in culpable delay when the event triggering the extension of time occurs.
(b) An extension of time will usually be added contiguously to the previous date for completion, not discontinuously in discrete periods of time. However, this does not apply where the contractor is in culpable delay when the event triggering the extension of time occurs. In these circumstances any extension of time will be added as a discrete period.
(a) A court can never have recourse to deleted or omitted wording when interpreting a contract.
(b) A court can refer to deleted words in a printed, standard form to resolve the ambiguity of a neighbouring paragraph that remains.
(c) A court can refer to deleted words to resolve ambiguity even if no printed form is involved.
"The diversity of authority… renders it difficult for a judge of first instance to recognise when recourse to deleted words may properly be made. The tenor of the authorities appears to be that in general such recourse is illegitimate, save that (a) deleted words in a printed form may resolve the ambiguity of a neighbouring paragraph that remains; and (b) the deletion of words in a contractual document may be taken into account, for what (if anything) it is worth, if the fact of deletion shows what it is the parties agreed that they did not agree and there is ambiguity in the words that remain. This is classically the case in relation to printed forms (Mottram Consultants, Timber Shipping, Jefco Mechanical Services), or clauses derived from printed forms (Team Service), but can also apply where no printed form is involved (Punjab National Bank Ltd)."
(a) Concurrent delay, in the context of construction and engineering projects, is a period of delay that is caused by two events, one the contractor's contractual responsibility and one the employer's contractual responsibility. It is unnecessary for the events causative of delay to occur simultaneously, but the consequences of the two events must be felt at the same time.
(b) Concurrent delay, in the context of construction and engineering projects, is a period of delay that is caused by two events, one the contractor's contractual responsibility and one the employer's contractual responsibility and both the events causative of delay occur simultaneously and the consequences of the two events are felt at the same time.
(c) Concurrent delay, in the context of construction and engineering projects, is a period of delay that is caused by two or more effective causes of delay which are of approximately equal causative potency.
(d) In cases of concurrent delay the contractor is entitled to an extension of time but is not entitled to recover any time-related costs.
(e) On the first day of Christmas my true love gave to me, two turtle doves.
(a) You can refer the same dispute to different adjudicators.
(b) You can refer different disputes to the same adjudicator at the same time.
(c) You can refer different disputes to the same adjudicator, as long as you don't do it at the same time.
(d) You can refer different disputes to different adjudicators at the same time.